Plains All American
(Louisiana)
Babcock Eagleton, Inc. provided all design engineering,
survey and construction management for the Plains grass
roots St. James Terminal located in St. James Parish, La.
This storage facility includes tankage with a capacity of
two million barrels, metering with prover capabilities, and
interconnecting piping for several area plants. The
facility is fully automated. Babcock Eagleton, Inc.
designed/engineered the entire facility, including all
interconnecting pipelines.
Air Products & Chemicals,
Inc.
(Texas)
Babcock Eagleton, Inc. performed a lump sum turnkey project
on the installation of 62 miles of 10” pipeline carrying
industrial gases. The project route went from Bayport
Industrial complex to Freeport, Texas. Babcock Eagleton,
Inc. provided survey, right-of-way acquisition, design
engineering, permit acquisition, procurement, construction
management, inspection and contracting. Project included
three meter stations and twenty-three valve stations.
TE Products Pipeline
Company
(Texas)
Babcock Eagleton, Inc. performed a lump sum turnkey project
for the installation of three parallel 12-inch pipelines
approximately 68 miles in length from Port Arthur to Mont
Belvieu including eleven custody transfer quality meter
stations. The project started with initial estimates for
TEPPCO to commercially develop the project with their
clients, Fina and BASF, and was then converted to an LSTK
project. Babcock Eagleton, Inc. performed survey,
right-of-way acquisition, design engineering, permit
acquisition, material procurement, construction management,
inspection, and construction contracting to complete the
project.
Lavaca Pipe Line Company
(Texas)
Babcock Eagleton, Inc. provided engineering design and
right-of-way acquisition for the installation of 45 miles of
12-inch ethane pipeline from Mont Belvieu to Texas City
under a lump sum engineering contract to Lavaca. Project
work included all necessary survey and title work to procure
the pipeline route; all permitting for three counties, the
Army Corps of Engineers, nine municipalities, and several
other state and local authorities; development of all
material specifications and requisitions; and preparation of
the construction bid package.
Mobil Oil Company
(Texas)
Babcock Eagleton, Inc. provided engineering services for the
upgrading of several pump stations on a Mobil crude oil
pipeline system in East Texas. The upgrades included the
installation of variable frequency drive systems for ten
pump stations varying in size from 500 horsepower to 5,000
horsepower. Babcock Eagleton, Inc. completed all design work
through the issuance of material requisitions and
construction bid packages.
UNOCAL
(Texas)
Babcock Eagleton, Inc. provided engineering services for the
installation of a high volume crude oil pump station
containing two 3,000 horsepower pumps at the Nederland
facilities. The pumps were designed with a variable
frequency drive to operate in a synchronous mode. The
station work included the addition of three meter systems
and interconnecting piping.
Petro Source Carbon
Company
(Texas)
Babcock Eagleton, Inc. provided a lump sum turnkey project
for the installation of 82 miles of 10-inch CO2 transmission
pipeline in West Texas. The system included the installation
of a 1,000 horsepower electric motor driven pump station,
custody transfer metering, and a SCADA system for the
pipeline. Babcock Eagleton, Inc. handled all facets of the
project from route selection, right-of-way acquisition and
permitting to material procurement, construction contracting
and system commissioning.
Pennzoil
(Texas)
Babcock Eagleton, Inc. provided engineering services for the
installation of two 1,000 horsepower centrifugal pump
station upgrades, the addition of five custody transfer
meter stations, and the implementation of a SCADA system on
their West Texas CO2 transmission system. Engineering work
included all design work with a seasonal impact hydraulic
analysis of the system capacity, preparation of
specifications and procurement for all materials, assembling
the construction bid packages and corresponding contracts,
and commissioning of the SCADA system.
Equistar Chemical LP
(Texas)
Babcock Eagleton, Inc. provided engineering services for the
installation of a new 800 HP pump station, meter station and
5 pipeline laterals required to ship mixed C4 product from
La Porte to Mont Belvieu. The project included the
installation of a new 12 KV/4160 V indoor substation.
Babcock Eagleton, Inc. provided design engineering including
right-of-way acquisition, permitting work, preparation of a
detailed construction package, and material requisitions and
procurement.
Transpetco
(New Mexico, Texas, Oklahoma)
Babcock Eagleton, Inc. provided route selection, surveying,
mapping, permit application, right-of-way acquisition,
pipeline and meter station design, material specifications,
contract specification documents, field engineering,
construction inspection, as-built survey and drafting for a
CO2 pipeline. The project consisted of approximately 102
miles of 12-inch pipeline, 9 mainline block valve sites,
launcher/receiver facilities, meter stations, and a booster
station facility.
Diamond Shamrock
(Texas)
Babcock Eagleton, Inc. performed a complete turnkey project
for a complex 8-inch pipeline system in the Bayport area.
The pipeline system originates at an existing Diamond
Shamrock pipeline and continues to a delivery meter station
at the Texas City terminus. The project consisted of 19
miles of an 8-inch pipeline with 5 mainline block valves and
a metering facility. The line had several directional drills
including a complex 2400 foot drill across Clear Creek at
the entrance to Clear Lake.
Marathon Oil Co.
(Louisiana)
Babcock Eagleton, Inc. prepared the scope of work, cost
estimates, detailed engineering and design, equipment and
material specifications, and material procurement for the
Nautilus Pipeline Onshore Facilities. These facilities
include a 4400 BBL liquid slug catcher, 30-inch pipeline
sphere receiver and sphere storage/handling area, condensate
pumps, control buildings, warehouse, automated PLC control
system and extensive sales metering for various customers
throughout Southern Louisiana.
BASF
(Texas)
Babcock Eagleton, Inc. provided route selection, surveying,
mapping, permit application, right-of-way acquisition,
pipeline and meter station design, SCADA system design,
material specifications, contract specification documents,
field engineering, construction inspection, as-built survey
and drafting for a propylene pipeline system. The project
consisted of approximately 57 miles of 8-inch pipeline, 10
mainline block valve sites, metering facilities, manifolding
for intermediate tie-ins, launcher/receiver facilities, and
a SCADA system.
Amerada Hess Corporation
(North Dakota)
Project management, surveying, engineering design, material
procurement, and construction management for two natural gas
compressor stations and a transmission pipeline. One station
was a grass roots station with three 1,340 HP gas turbine
driven centrifugal compressors and waste heat recovery
boilers; the station was designed with a PLC-based control
system for unattended operation. One existing compressor
station with two 800 HP integral gas engine driven
reciprocating compressors was completely modified for
pipeline service; modifications included new station and
unit piping and valving, custody transfer meter, and
replacement of pneumatic engine/compressor controls with an
unattended PLC-based control system. The project also
included approximately 62 miles of 10-inch pipeline, five
miles of 8-inch pipeline, five miles of 6-inch pipeline, and
58 miles of fiber optic cable installed with the pipelines.
One 10-inch and two 8-inch pipelines and a fiber optic cable
were simultaneously installed across a 2.2 mile wide lake.
Amerada Hess Corporation
(New Mexico)
Babcock Eagleton, Inc. prepared budgetary cost estimates for
preliminary and alternate route selections for a proposed
carbon dioxide transmission pipeline system consisting of
five 12 through 20-inch lines traversing 16.5 miles. In
addition, Babcock Eagleton, Inc. prepared detailed drawings
and material specifications for interconnecting piping at
each end of the pipeline system including complete
monitoring for the pipeline system. Babcock Eagleton, Inc.
also assisted Amerada Hess in evaluating metering systems at
each location.
Amerada Hess Corporation
(North Dakota)
Babcock Eagleton, Inc. prepared a complete cost analysis
encompassing all estimated costs of transporting carbon
dioxide via a proposed pipeline from the Great Plains Coal
Gasification Facility to delivery points within the
Williston Basin of North Dakota.
Amerada Hess Corporation
(Texas)
Project management, surveying, engineering design, material
and construction management for approximately nine miles of
10-inch pipeline transporting hydrocarbon saturated gas. The
system receives gas from a well at 1,250 psig and delivers
to two independent pipelines at a delivery pressure of 800
psig.
Tenneco Gas
(New York)
Addition of a 4,000 HP integral reciprocating gas compressor
at each of two existing mainline compressor stations.
Transco Energy Marketing
Company
(Louisiana, Texas)
1. Babcock Eagleton, Inc. performed a complete grass roots
design and procurement of a 4,000 BPD hydrocarbon condensate
fractionation plant producing naphtha, LPG, and heavy oil.
The project included detailed design, drafting, construction
inspection and start-up. The entire project was designed and
constructed within 12 months.
2. Babcock Eagleton, Inc. performed engineering design,
procurement, and inspection services for a 15,000 BPD
condensate stabilization facility. Included were facilities
for recompression of off-gas and storage facilities for
stabilized condensate.
West Texas Utilities
Company
(Texas)
Babcock Eagleton, Inc. provided project management,
drafting, engineering design, inspection services and
start-up for approximately 23 miles of 12-inch natural gas
pipeline. The system includes a tie-in to existing supply
lines with metering facilities, liquids separation, and
pressure regulation facilities.
BP Pakistan, Inc.
(Pakistan)
1. Babcock Eagleton, Inc. provided two-phase flow studies to
determine pipeline sizing, pressure drop, liquid hold-up,
slug volumes and slug catcher design of approximately 140
miles of transmission and collective lateral pipeline
systems.
2. Complete engineering design (mechanical, civil,
instrument, electrical) and drafting services for a 60
MMSCFD, 1,500 BPD gas/liquid separation facility. Plant
facilities included condensate stabilization, overhead
compression, product storage/metering and truck loading, gas
dehydration and sales metering as well as power generation.
3. Detailed design including process simulations for a
remote separation facility, eight miles of 6-inch two-phase
pipeline, and addition of separation facilities at a central
gas/liquid separation/stabilization plant. These facilities
were designed for 40 MMSCFD and 2,000 BFPD. Equipment
included test and production separators, production
manifold, pig launcher/receiver, 60” ID x 30’s/s 8-trayed
gas contactor as well as all well site facilities.
4. Complete engineering design (mechanical, civil,
instrument, electrical) and drafting services for a 30
MMSCFD, 1,000 BPD gas/liquid separation facility. Plant
facilities included condensate stabilization, overhead
compression, product storage/metering and truck loading, gas
dehydration and sales metering as well as power generation.
5. Engineering and drafting services including complete
process simulations for remote and in-plant separation
facilities as well as detailed evaluation of an existing 50
MMSCFD gas/liquid separation and stabilization facility to
determine design changes required to enable this facility to
process 80 MMSCFD. This project included the design of a new
test separator, production separator, launcher/receiver,
five miles of 8-inch two-phase pipeline to handle 60 MMSCFD
and 2,000 BFPD of new production. Modifications to existing
piping, instrumentation, and valves as well as a new 4.0
MMBTU/Hr glycol regeneration skid at the central separation
plant were also part of the project.
6. Complete engineering design and drafting services for a
6,000 BPD production facility. The oil facility included
test/production separators, manifold and interconnecting
pipe header skids, six 2,000 barrel oil storage tanks and
truck loading facilities. The total facility, including all
equipment skids, were designed to facilitate field expedient
assembly and disassembly to enable the plant to be moved to
other locations.
7. Detailed design of firewater system including 10,000
barrels of above-ground firewater storage tanks and a 1,350
GPM firewater pump.
8. Babcock Eagleton, Inc. provided engineering design,
drafting and inspection for a 100 MMSCFD gas/liquid
separation facility. Sustaining facilities include a 500 BBL
slug catcher, liquid stabilization and storage, pressure
reduction station, and manifolding into existing gas
metering facilities.
Diamond Shamrock Refining
and Marketing Company
(Texas)
Babcock Eagleton, Inc. has performed many projects involving
a wide spectrum of services for Diamond Shamrock. A summary
follows:
1. Bay Area Petrochemical Pipeline – Babcock Eagleton, Inc.
provided route selection, surveying, mapping, permit
acquisition, pipeline and meter station design, material
specification, contract specification documents, field
engineering, construction inspection, as-built survey and
as-built drafting. The project consisted of approximately 16
miles of 6-inch pipeline complete with launcher and
receiver, mainline block valve stations, and a meter station
for the delivery of propylene from Mont Belvieu, Texas to
the Deer Park area. The line has several directional drills
including a 2,200 foot crossing of the Houston Ship Channel
and also approximately 4,500 feet placed by jetting across
Crystal Bay.
2. Babcock Eagleton, Inc. provided project management,
design engineering, surveying, mapping, design drafting,
permit acquisition and construction management for two miles
of 6-inch propylene pipeline in Mont Belvieu, Texas. The
design included a tie-in to the existing Bay Area
Petrochemical Pipeline, two 1,000 foot long, directionally
drilled crossings, and a meter skid station at the in-plant
pipeline terminus.
3. Babcock Eagleton, Inc. provided research, engineering,
surveying and mapping services necessary to consolidate and
coordinate information required by state and federal
regulations on a number of existing, newly acquired, and
inadequately documented pipelines in the congested Mont
Belvieu, Texas area. The project produced approximately 50
alignment drawings and detail aerial sheets covering 22
separate pipelines.
4. Babcock Eagleton, Inc. performed numerous pipeline
feasibility studies in the Gulf Coast area. Such studies
involved route selections, permit/right-of-way development,
capital cost studies and conceptual engineering studies.
ITR Petroleum, Inc. –
General Atlantic Energy
(Wyoming)
Babcock Eagleton, Inc. performed a turnkey project
consisting of approximately 40 miles of 16-inch gas mainline
and 12 miles of 4, 6, 8 and 12-inch gathering pipelines
connecting 28 well sites in Southeast Wyoming.
Responsibilities included route selection, right-of-way
acquisition, permitting, engineering design, drafting,
material purchasing and field receipt, construction
management and system start-up. Babcock Eagleton, Inc.
performed the entire project for a lump sum.
Intercontinental Terminals
Company
(Texas)
Project management, engineering design, drafting, survey and
construction inspection on a containment pipeline system for
aniline. One of the few contained pipeline systems ever
designed, the ITC system involves a 6-inch carrier pipe
completely fabricated inside a 10-inch annulus pipe. Entire
pipeline length of 3.5 miles is monitored by an infrared gas
analyzer to detect aniline leaks. A specialty pipeline
designed and constructed under Babcock Eagleton, Inc.
supervision in the Deer Park, Texas area.
Intercontinental Terminals
Company
(Texas, Florida)
Babcock Eagleton, Inc. has performed numerous plant surveys
and associated drafting services since 1985 for both the
Deer Park, Texas and Orlando, Florida facilities.
Enron Corporation
(Texas, Wyoming, Iowa, Oklahoma, New Mexico, Florida,
Kansas)
Babcock Eagleton, Inc. has performed in excess of 64
projects for Enron Corporation since 1986. A partial summary
follows:
1. Redfield Plant – Engineering design, drafting, and
construction inspection of additional amine treatment
facilities, meter facilities, and heater facilities.
2. Atoka Station – Engineering design, drafting, and
construction inspection of dual scrubber facilities on the
Transwestern System.
3. Pipeline system feasibility study consisting of route
selection and capital cost development for a 190 mile gas
pipeline in Kansas.
4. Nueces Compressor Station – Project management, detailed
design engineering, drafting and construction supervision
for a 3,000 HP compressor station.
5. Waterloo Station – Engineering design and drafting for
jacket water system and related water pump additions.
6. Engineering design, drafting, and project management for
piping modifications and meter facilities at the Mullinville,
Bushton, Eagle, West St. Cloud and Lakeville Stations.
7. West Palm Beach Station – Project management, engineering
design, drafting and construction supervision for a meter
station and associated piping.
8. Mitchell Compressor Station – Project management,
engineering design, drafting and construction inspection for
a compressor unit addition relocated from another Enron
station.
9. Bitterlake – Provided engineering design, material
specifications, and drafting to relocate a 2,250 BHP
compressor complete with associated equipment and piping,
500 BBL slug catcher, and modifications to yard piping.
10. Yates Horsepower Addition – Provided engineering design,
material specifications, and drafting for modifications to
yard piping and installation of an 800 BHP compressor to an
existing station.
11. Bloomfield Compressor Station – Project management,
engineering design, and drafting for a grass roots metering
and turbine driven centrifugal compressor station with a
total installed horsepower of 9,000 and a design rate of 520
MMSCFD.
Chevron Pipeline Company
(Texas)
Survey and associated drafting services for various pipeline
and station facilities. Babcock Eagleton, Inc. provided
certified centerline and boundary descriptions for a variety
of projects.
Chevron U.S.A., Inc.
(Texas)
1. Babcock Eagleton, Inc. provided research analysis of
Texas pipeline infrastructure, assisting Chevron U.S.A. with
product delivery and storage feasibility investigations.
2. Babcock Eagleton, Inc. performed a research feasibility
study analyzing the possibility of interconnecting
neighboring natural gas supply pipelines with Chevron
Refinery. Four alternative scenarios complete with SCADA
monitoring were investigated and estimated.
Celanese Chemical Company
(Texas)
Project management, design engineering, drafting and
construction management for the refurbishing of a propylene
pipeline system. Babcock Eagleton, Inc. was retained to
provide engineering services to update an old propylene
system and bring it up to present code requirements.
Activities included line purging, installation of block
valves, and SCADA system.
Llano, Inc.
(New Mexico)
Engineering, drafting, material procurement, survey,
construction supervision and start-up assistance for the 33
mile, 12-inch Llano CO2 pipeline.
CITGO Pipeline Company
(Texas)
Project management, surveying, engineering, design,
construction inspection of 100 mile, 10 to 12-inch gas
pipeline from Lake Charles, LA to Mont Belvieu, TX.
TOGCO Natural Gas Storage
Corporation
(Oklahoma)
Babcock Eagleton, Inc. provided, on a contract engineering
basis, a senior project manager to develop and oversee a 40
mile, 20-inch pipeline system in Oklahoma. Subsequently,
Babcock Eagleton, Inc. also performed the pipeline survey
activities and construction inspection for the project.
Chevron Pipeline Company
(Texas)
Project management, surveying, engineering, design, material
acquisition, and as-built documentation for 16 miles of
10-inch ethylene pipeline from Mont Belvieu to Deer Park,
Texas.